Construction Steps
1. Prep & Foundation
Rough Grading
Cut Driveway
Gravel Driveway
Get Water Meter (or dig well)
Clear Home Site plus work area
Install Temp Power Pole
Crawl Space or Basement
Batter Bonds
Dig Foundations
Pour Footings
Lay Block or Pour Walls
Pre-treat for termites
Waterproof or backfill
Slab and Garage
Form Boards
Plumbing
Misc Pipes
Gravel
Poly Vapor
Pre-Wire
Pour Concrete
Spot Foundation Survey
Gas, Sewer & Misc Utility lines
What should be done by this point :
Kitchen and Bath cabinets should be ordered. (make sure that company is willing to store them for you. They can take up to 6 months lead-time)
2. Framing
Building Level
Check Foundation Level/Square
Check Level/Square Again
Have Framing Materials Delivered
Maintain Materials Supply
Cull Materials
Basement Wall & Beams
Subfloor, 1st Floor
Subfloor, 2nd Floor
Set Special Tub, 2nd Floor
Walls / Partitions, 2nd Floor
Check Level, Square & Layout as work progress
Ceiling Joists
Rafters & Trusses
Roofing Sheathing and Felt
Framing Inspection
Install Doors/Windows
Measure Cabinets
Know what needs extra blocking : heavy window treatments, light fixtures, mirrors
Know if you have tile niches, recessed medicine cabinets
Exterior Masonry
Schedule Delivery of Exterior Windows, Doors, Siding and Trim
Install Doors
Install Windows
Install Factory Built Fireplace
Misc. Rough Frame and Deadwood
What should be done by this point :
Order plumbing because the valves need to be put in at the rough-in phase Install Brick/Stone if any specified
Order Plumbing,
Tile
Finalize Lighting
3. Rough Ins / Rough Mechanics
Plumbing Rough (Is this always first?)
Specific Plastic or Cooper Pipes
Rough In for Bath, Kitchen etc
Pay only after is inspected
Heating & Cooling Rough
Take Floor Plan to Power Co for size of system (smaller systems are more efficient, large houses use multiple systems)
Rough-In Heating/Cooling
Get Rough-In approved by building inspector before paying for service
Electrical Rough
Get approved for Wiring Plan
Get power Co to recommend how much Amp service is needed
Rough In Wiring
Talk about conduits for future use
Pay for Rough In only after Inspection
What should be done by this point :
Get prepared to order all custom furniture, rugs and window treatment fabric by the end of month 6.
Get yardage requirements for window treatments. Fabrics can be backordered and it is good to get this done in advance.
If you haven’t already
Order kitchen and bath cabinets
Order Interior Door Hardware
Reserve (inspect) and buy all counter slabs
Tile must be ordered.
4. Drywall & Insulation
Insulation
Get Powder Co to determine amount of R valve and Insulation needed
With Blow in Insulation fo not clock off soffit vents
Ceiling & Wall Covering (this seems lacking…blueboard vs. drywall.. Do they always plater?)
Install Drywall
Plater
Clean Interior
What should be done by this point :
Complete Paint Schedule
Do samples of wood stains on pieces of the wood being used on the floors.
Measure for Rugs and Order once baseboard is installed
Measure and Order WT hardware once window casings are installed
5. Interior Finishes
Install Wood and Tile Flooring (that cabinets need to be installed over). Is this true for Engineered floors?
Hire a master carpenter (I think this should be discussed and designed before)
Stain or pretreated paint grade trim
allow 1/2” space under baseboard for carpet. (Should this be 1/4”)
Install Interior Doors and door hardware
This is a good time to see if you need to bring in any furniture that is so large it can’t be brought up when stair railing is put up or door casings are in.
Install Cabinets
Note about them settling in space for a few days
At what point when framing is done to you confirm interior wall lengths. Need to take into account lighting outlet locations and window and door casings)
Recommend caulking around window and door trim inside and out
Schedule Counter Templating as soon as they will allow you
Finish the Fireplace
Measure for all bath thresholds and sills and Order
Counter Templating
You will want sink and faucet onsite. They will take sink with them
Install Counters
Install remaining tile, backsplashes and stone floors
Interior Paint
6. Exterior Work
7. Final Trades
Hang Wallpaper
Call back plumbing, electrical and Heating
Cooling Contractors for Final Work
After final Inspection, utilities can be turned on (Power may be required prior to final inspection)
Install Wall to Wall Carpet.
Install Mirrors, Shower Glass and Bath Accessories
Install Gutters and Screens
Landscape, Drives, Walks, Patio, Etc
Final Inspections
Final Inspection
Fix Little Nicks, touch up paint, clean windows, floors, etc
***When fo appliances get installed.
8. Flooring Completion
9. Certificate of Occupancy
10. Interior Install (Month 13 and ….)
Rug Install
Window Treatment Hardware Install
Furniture Delivery
Window Treatment Install (panels and romans)